WORK ACTIVITY JOB START COMPLETION LOCATION

Refurbish of Jungle House Playground

Note: The Jungle House room is still open for activities/lessons

29 January 2024 28 April 2024 Jungle House Playground
Replacement of roofing  1 March 2024 15 March 2024 Dance Hall
Replacement of roofing 16 March 2024 9 April 2024 Facing Golf Course
Replacement of roofing 10 April 2024 15 May 2024 Facing Tennis Court
 
Members are advised to observe safety signage. Safety barriers are erected to restrict members' access to worksite. It is the responsibility of all members to observe these restriction barriers and not allowed children near the worksite.