Buggy Pathway Construction Notice
Dear Members and Guests,
The construction work on the new buggy pathway will commence on Tuesday, 30 June 2026.
The project is expected to take approximately 1.5 months to complete. During this period, there may be some temporary disruptions on certain parts of the course.
| Location | Duration |
|---|---|
| Green 1 to Tee Box 2 | 4 Days |
| Tee Box 2 to Fairway 2 | 2 Days |
| Tee Box 3 to Fairway 3 | 9 Days |
| Green 3 to Tee Box 4 | 3 Days |
|
Bridge Near Canteen (Raising and Concreting Works) |
5 Days |
| Pathway Near Canteen | 14 Days |
| Ladies Tee Box 6 to Fairway Bridge | 5 Days |
| Trees Across Bridge & Back to Fairway | 7 Days |
| Hole 16 Green | 5 Days |
We kindly ask for your patience and cooperation as we work to improve your golfing experience.
Thank you for your understanding and support.