Buggy Pathway Construction Notice

Dear Members and Guests,

The construction work on the new buggy pathway will commence on Tuesday, 30 June 2026.

The project is expected to take approximately 1.5 months to complete. During this period, there may be some temporary disruptions on certain parts of the course.

Location Duration
Green 1 to Tee Box 2 4 Days
Tee Box 2 to Fairway 2 2 Days
Tee Box 3 to Fairway 3 9 Days
Green 3 to Tee Box 4 3 Days
Bridge Near Canteen
(Raising and Concreting Works)
5 Days
Pathway Near Canteen 14 Days
Ladies Tee Box 6 to Fairway Bridge 5 Days
Trees Across Bridge & Back to Fairway 7 Days
Hole 16 Green 5 Days

We kindly ask for your patience and cooperation as we work to improve your golfing experience.

Thank you for your understanding and support.