Buggy Pathway Construction Notice
Dear Panaga Club Members,
The construction work on the new buggy pathway will commence on Monday, 11th August 2025.
The project is expected to take approximately 8 weeks to complete. During this period, there may be some temporary disruptions on certain parts of the course.
Location | Duration |
Tee Box #9 to buggy track #9 | 10 Days |
From bridge to tee box #10 near boatshed | 14 Days |
From buggy shop to Green #8 | 10 Days |
From tee box bridge #17 to Fairway Bridge #17 | 10 Days |
Near Tee Box #3 to Paver #8 (Behind Green 2) | 12 Days |
We kindly ask for your patience and cooperation as we work to improve your golfing experience.
Thank you for your understanding and support!